Steelwork Gantry Extension detailed, fabricated and installed by AM Fabrication (Northern) Ltd 2 days ahead of Programme. Well Done to our Site Supervisor Keith for your efforts on site.

#StructuralSteelwork

#SecondarySteelwork

#OpenDeckFlooring

#DataCentre

#Specialist

#DesignTeam

#Programme

MicrosoftTeams-image (3).png

September 2019

 

Reaching a new Level!

 

We are currently 45metres up on our current project 50metre high project.

Well done to Keith and the team for working safely and maintaining programme on a complex project.

#50mHigh

#StructuralSteelwork

#Working@Height

#Specialist

#DesignTeam

2.jpg

August 2019

 

Steelwork progressing nicely for one our continued valued Data Centre Clients.

Next Phase to progress with fabrication and installation of the secondary roof steelwork and internal staircases.

#StructuralSteelwork

#Confinedsite

#DataHall

#Datacentre

#DesignTeam

#Fabrication

#Steelerection

1.jpg

 

March 2019

 

Our first load of steelwork erected and progressing nicely at Newcastle Airport.

Tricky little structure to detail, fabricate and erect.

#StructuralSteelwork

#Meet&Greet

#RadiusItems

#RolledItems

#DesignTeam

#Fabrication

#Steelerection

NIAL.jpg

 

February 2019

Reaching new Heights!

 

We are currently 32metres up on our current project 50metre high project.

 

Well done to Stevie and the team for working safely and maintaining programme on a complex project.

#50mHigh

#StructuralSteelwork

#Working@Height

#Specialist

#DesignTeam

#Fabrication

#Steelerection

#OnProgramme

#Fabrication

DSC05736.JPG
DSC05740.JPG
file9.jpeg
file-11.jpeg

January 2019

 

 

A New Year another Data Centre!

 

Site erection has started with the erection of the first load of twelve on our current Data Centre project.

 

Well done to Richie and the team for another safety award.

 

 

#Datacentre

#StructuralSteelwork

#London

#Specialist

#DesignTeam

#Fabrication

#Steelerection

#Anothersafetyaward

#Fabrication

1.jpg
2.jpg
23_24 Data Hall Handover_Gridline 7 and

October 2018

 

 

AM Fabrication are proudly in our 13th year of working on Brighton Palace Pier.

 

 

AM Fabrication continue working under the Pier, keeping this iconic British landmark in good health for future generations.

 

Refurbishment works include replacement trusses, rails and bracings.

 

 

#BrightonPalacePier

#Marine

#CostalDivision

#Specialist

#Costalworks

#RopeAccess

#Fabrication

Brighton.jpeg

September 2018

 

AM Fabrication (Northern) Ltd Appoint Technical Director.

AM Fabrication would like to congratulate and extend our warmest of welcomes to Matthew Reed, who has recently been appointed as the new Technical Director of AM Fabrication (Northern) Limited. 

 

Matthew has been with AM Fabrication for 2 years and has been promoted from Design Manager bringing a vast wealth of knowledge and expertise from within the steel industry.

 

Speaking about his new appointment Matthew said: '' I am delighted to have accepted the role of Technical Director at AM Fabrication we have an extremely busy 2018-2019 forecast. This is a very exciting time for the business.''

#TechnicalDirector

#AppointmentofDirector

#StructuralSteelwork

#SecondarySteelwork

 

Business Handshake

September 2018

 

Stainless, Glass, Architectural........

 

Another Secondary steelwork detailed, fabricated and Installed by AM Fabrication.

 

 

#Wedontjustdostructuralsteelwork

#SecondarySteelwork

#Fabrication

#Architectural Metalwork

#StainlessSteel

#Glass

August 2018

 

 

Another complex structure detailed, fabricated and erected by AM Fabrication to program.

 

 

#StructuralSteelwork

#Fabrication

#Logistics

#Complexbuild

#Datacentres

#Anothersafetyaward

IMG-20180730-WA0005.jpg
IMG-20180730-WA0000.jpg

July 2018

Our second load of steelwork leaves our factory ahead of delivery to Stockholm, Sweden next week.

#Steelwork

#Logistics

#Datacentres

#Overseas

#Europe

#Structralsteelwork

June 2018 -** New Contract Award**

AM Fabrication (Northern) Limited are pleased to announce we have been fortunate enough to receive the go-ahead for a 520 tonne Leisure Centre in London. Not due on site until Oct but a cracking little project for our design team to get stuck into. #Tekla #BIM_Lv2 #AMFAB

#Steelwork

#Mainsupplier

#Structuralsteelwork

#Tekla

#DesignTeam

#Structralsteelwork

May 2018

A small local project completed on a very confined site.

#Anotherhappyclient

#Steelwork

#Mainsupplier

#Structuralsteelwork

#Logistics

#Fabrication

#Confinedspace
#Confinedspace

May 2018

AM Fabrication (Northern) Ltd are now members of SCI - The Steel Construction Institute

#Steelwork

#Mainsupplier

#Structuralsteelwork

#Secondarysteelwork

#Fabrication

#Datacentre

April 2018

Our first load of steelwork leaves our factory ahead of delivery to Stockholm, Sweden next week.

#Steelwork

#Logistics

#Datacentres

#Overseas

#Europe

#Datacentre
#Datacentre

November 2017

AM Fabrication (Northern) Ltd receive another safety award by ESGPLC on our WGC Data Hall 21 & 22 Project.

#SitesupervisorRichie

#AMF-ESGPLC

#Safety@work

#Anothersafetyaward

Safety at work

November 2017

AM Fabrication (Northern) Ltd receive an All Safety safety award by Willmott Dixon Construction for our safety working on projects Darlington Civic Theatre and Hitachi Test Line.

#SitesupervisorBryan

#AMF-WDC

#Safety@work

#Allsafe

#Darlingtoncivictheatre

#HitachiTestline

#Anothersafetyaward

Willmott Dixon Construction

October 2017

AM Fabrication (Northern) Ltd receive another safety award by ESGPLC on our WGC Data Hall 21 & 22 Project.

#Sitesupervisor

#AMF-ESGPLC

#Safety@work

#Anothersafetyaward

Safety at work

July 2017

AM Fabrication (Northern) Ltd receive a safety award by Vinci Construction on our NCGM Flower Market project in London.

#SteveMcCrystal

#AMF-Vinci

#Safety@work

#Anothersafetyaward

© 2019 AM Fabrication (Northern) Ltd                           Company Registration: 03707882                                Vat Registration: 733856119

#SafetyatworkAMF